Skip to main content

Hardware Installation

Although hardware installation usually is performed by Tessonics technician, it can be done by qualified person trained in Tessonics.

For installation are used the following parts:

  • RIWA CM with or without PC;
  • RIWA DC adapter and power cable;
  • Electrode with installed transducer;
  • Coaxial cable to connect transducer with the unit;
  • RIWA RM;
  • Industrial network cable to connect RIWA CM to the robot;
  • CAT6 cable to connect RIWA CM to the RM;
  • CSC or CSH;
  • CAT6 cable to connect CSC to the CM or to connect CSH to the RM;

RIWA CM with or without PC can be installed at any designated place or mounted on the enclosure. PLC program on the robot / weld controller need to be modified in order to provide input data for the RIWA system and accept output data (feedback) from the RIWA.

When the unit and electrode with the transducer were installed, all cables were connected and all settings and adjustments were done, on the PC start RIWA Client Module it will start function automatically.